News
» Go to news mainCampus Construction Update
The Campus Construction Update is a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices during summer construction.
June 26-29th
Remove old windows in section B (Rooms 140, 142, 242, 246)
Prep openings for new window installation in rooms noted above
Miscellaneous joint cutting on exterior of building on daily basis
The classrooms above should be considered closed during this time frame.
July 4th-7th
Install new windows in section B- (rooms 140, 142, 242, 246)
Remove old windows in section C (rooms 254, 255,257, female wash room second floor
All classrooms in section B and C should be considered closed during this time frame.
Thank you for your patience and understanding,
Ìý
Recent News
- Holiday Hours
- From Academia to Agriculture: Former PhD student and supervisor launch innovative vertical farming venture
- Community Representative ‑ Animal Care and Use
- New Face on Campus
- Sowing Seeds of Knowledge: A Gardener’s Journey with DeAnne Pelchat
- »ÆÉ«Ö±²¥ Advising Summit
- Legacy Awards 2024
- Fall Food Drive